BP110964 - 198 Holland

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP110964 - 198 Holland
Neighbourhood: Westwood    
Street Address: 198 Holland
Type of Application: Commercial / Multi / Industrial
File Number: BP110964
Date Application Submitted: December 06, 2006
Application Description: Nanaimo Christian School-New School,Group A-Division 2-Existing school west side of property to remain.New school divided by 2 hr firewall.North of firewall new BUILDING 1; Area 714m2,south of firewall new BUILDING 2: Area 61m2.Building classification 3.2.2.26 (either non-combustible or combustible construction permitted by code), prinklered,fire alarm system, using Non combustible construction,2 storey with basement,floor assembly between basement & 1st storey 45min FRR/FS,floor assembly between 1st storey & 2nd storey non-combustible construction fire separation only. 45 min FRR/FS for exits,elevator & elevator machine room machine room. Accessible for persons with disabilities.
BUILDING 2:61m2 is Building Classification 3.2.2.24,non combustible,
1 HR FRR/FS for floor assemblies.
Exposed building faces (tilt-up)=1 hour FRR on West Building face.
Total Floor areas=Basement 775 m2,1st Storey=789.8m2 & 2nd Storey = 789.8 m2.
Physical File Scanned + attached Nov 5, 2008 db
Application Status: COMPLETED
Permit Value: $2,900,000.00
Builder: RW (BOB) WALL LTD
Issued Date: July 30, 2007
File Close Date: March 14, 2008

Associated Properties

Address Zone More
198 HOLLAND ROAD CS1 Property Report

Process Steps

Task Status
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

CANCELLED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

CANCELLED
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PARTIAL
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

FAILED
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

PASSED
PLUMBING FINAL-OLD

All fixtures must be in place.

FAILED
PLUMBING FINAL-OLD

All fixtures must be in place.

PASSED
OCCUPANCY-OLD PASSED

2008-03-14

FINAL-OLD

Final approval as per requirements on plans.

PASSED

2008-03-14

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.