BP110920 - 2555 Bowen

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP110920 - 2555 Bowen
Neighbourhood: Diver Lake    
Street Address: 2555 Bowen
Type of Application: Commercial / Multi-Res Alteration
File Number: BP110920
Date Application Submitted: November 20, 2006
Application Description: Nanaimo Toyota add 375.7m2 of mezzanine area and reconfigure office areas on main floor, reconfigure 2 hr FS between repair garage and display/office area, move and reconfigure washrooms, add washrooms on mezzanine, sprinkler entire building. Equivalency by R. de Beeld for only one exterior exit from mezzanine >200m2, three other access stairs provided to the main floor. 3/4 hr FS for one exit to the exterior from the mezzanine.

Existing F-2 occupancy with fire alarm, one storey, 2 hour fire resistance rating required at separation between repair/lube areas and showroom/office, no rating at roof or mezzanine.
Now - One storey, sprinklered, combustible, 2217 m2 building main floor with 446.9m2 mezzanine.
1998 BCBC 3.2.2.72 applies

March 10, 07 Equivalency & Schedules submitted for water curtain protection of windows and overhead doors in 2hr fire separation by GHL. VS

Physical File Scanned + Attached June 13, 2008 db
Application Status: COMPLETED
Permit Value: $300,000.00
Building Area: 375.70 M2
4,044.00 ft2
Builder: ISLAND WEST COAST DEVELOPMENTS
Issued Date: March 06, 2007
File Close Date: February 05, 2008

Associated Properties

Address Zone More
2555 BOWEN ROAD COR3 Property Report

Process Steps

Task Status
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PASSED
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PARTIAL
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PASSED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

PARTIAL
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

PASSED
PLUMBING FINAL-OLD

All fixtures must be in place.

PARTIAL
PLUMBING FINAL-OLD

All fixtures must be in place.

PASSED
FINAL-OLD

Final approval as per requirements on plans.

FAILED
FINAL-OLD

Final approval as per requirements on plans.

PASSED

2008-02-05

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.