BP110764 - 6000 Uplands (Parent) Inspections Only 6196 Washington Way (1) -- Scanned

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP110764 - 6000 Uplands (Parent) Inspections Only 6196 Washington Way (1) -- Scanned
Neighbourhood: Rutherford    
Street Address: 6000 Uplands (Parent) Inspections Only 6196 Washington Way (1) -- Scanned
Type of Application: Commercial / Multi / Industrial
File Number: BP110764
Date Application Submitted: October 03, 2006
Application Description: Strathcona Estates - Washington Way - Multi family development - 14 sfd houses in 3 phases. Phase 1 - units 1 to 5, one & one half storey and two storey sprinklered single family dwellings on crawl space with attached unsprinklered garages. Landscape bonding for 5 units & retaining wall under this permit. On and off-site servicing under BP110689.

6196 Strathcona Place - Unit 1, 180 m2 gross floor area, 41.7m2 garage
Inspection tasks for Unit 1 under BP110764 + all fees, attributes etc.

6207 Washington Way - Unit 2, 178.4m2 gross floor area, 41.5m2 garage
Inspection tasks for Unit 2 under BP111022

6208 Washington Way - Unit 3, 180.6m2 gross floor area, 42.9m2 garage
Inspection tasks for Unit 3 under BP111023

6211 Washington Way - Unit 4, 149.5m2 gross floor area, 41.5m2 garage
Inspection tasks for Unit 4 under BP111024

6212 Washington Way - Unit 5, 180.6m2 gross floor area, 42.9m2 garage
Inspection tasks for Unit 5 under BP111025

Doreen has file May 6, 2009
Application Status: COMPLETED
Permit Value: $985,000.00
Builder: KUNA ENTERPRISES LTD
Issued Date: January 24, 2007
File Close Date: February 05, 2008

Associated Properties

Address Zone More
6196 STRATHCONA PLACE R8 Property Report
6000 UPLANDS DRIVE R8 Property Report
6211 WASHINGTON WAY R8 Property Report
6212 WASHINGTON WAY R8 Property Report
6207 WASHINGTON WAY R8 Property Report
6208 WASHINGTON WAY R8 Property Report

Process Steps

Task Status
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PASSED
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PASSED
STORM CONNECTION

Pipe and connection must be visible for inspection.

PASSED
SANITARY CONNECTION

Pipe and connection must be visible for inspection.

PASSED
WATER CONNECTION

Pipe and connection must be visible for inspection.

PASSED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PASSED
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PARTIAL
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PASSED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PASSED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PASSED
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

PARTIAL
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

PASSED
OCCUPANCY-OLD FAILED
OCCUPANCY-OLD PASSED

2008-02-15

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.