BP110644 - 4800 Hammond Bay
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP110644 - 4800 Hammond Bay | |
|---|---|
| Neighbourhood: | North Slope |
| Street Address: | 4800 Hammond Bay |
| Type of Application: | Commercial / Multi / Industrial |
| File Number: | BP110644 |
| Date Application Submitted: | August 31, 2006 |
| Application Description: |
Foundation and on-site servicing only - 4 duplexes Units 1 & 2 and Units 3 & 4 (2 storey at front, slab-on grade) Unit 5 & 6 and Units 7 & 8 (2 storey at rear only , slab on grade and crawl space) Physical File Scanned + attached Aug 13, 2008 db |
| Application Status: | COMPLETED |
| Permit Value: | $200,000.00 |
| Builder: | IRA LEWIS CONSTRUCTION LTD |
| Issued Date: | October 12, 2006 |
| File Close Date: | February 05, 2008 |
Associated Properties
| Address | Zone | More |
|---|---|---|
| 4800 BRIDGEWOOD CLOSE | R6 | Property Report |
| 4814 BRIDGEWOOD CLOSE | R6 | Property Report |
| 4820 BRIDGEWOOD CLOSE | R6 | Property Report |
| 4819 BRIDGEWOOD CLOSE | R6 | Property Report |
| 4813 BRIDGEWOOD CLOSE | R6 | Property Report |
| 4807 BRIDGEWOOD CLOSE | R6 | Property Report |
| 4801 BRIDGEWOOD CLOSE | R6 | Property Report |
| 4802 BRIDGEWOOD CLOSE | R6 | Property Report |
| 4808 BRIDGEWOOD CLOSE | R6 | Property Report |
Process Steps
| Task | Status |
|---|---|
|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
CANCELLED |
|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
|
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PARTIAL |
|
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
|
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PARTIAL |
|
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
|
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
|
STORM CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
|
STORM CONNECTION
Pipe and connection must be visible for inspection. |
PARTIAL |
|
STORM CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
|
STORM CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
|
STORM CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
|
SANITARY CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
|
SANITARY CONNECTION
Pipe and connection must be visible for inspection. |
FAILED |
|
SANITARY CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
|
SANITARY CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
|
SANITARY CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
|
WATER CONNECTION
Pipe and connection must be visible for inspection. |
PARTIAL |
|
WATER CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
|
WATER CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
|
WATER CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
|
WATER CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
|
FINAL-OLD
Final approval as per requirements on plans. |
PASSED
2008-02-05 |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

View in Google Earth (KML)