BP110533 - 433 Poplar
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP110533 - 433 Poplar | |
|---|---|
| Neighbourhood: | Newcastle/Brechin |
| Street Address: | 433 Poplar |
| Type of Application: | Single / Two Family Dwelling |
| File Number: | BP110533 |
| Date Application Submitted: | August 08, 2006 |
| Application Description: |
Add 2 x 12 ft bay window at front, and 4 x 8 ft front entrance foyer with 3 x 8 ft covered entry porch to existing single family dwelling. 2009-Jan-21 - BP renewed - work cannot be completed due to weather. First inspetion to be called by 2009-Mar-09. Work to be complete by 2010-Sep-08. No more than 1 year between inspections after first inspection. |
| Application Status: | COMPLETED |
| Permit Value: | $15,000.00 |
| Building Area: |
51.28 M2 551.97 ft2 |
| Builder: | COPPER CONSTRUCTION LTD |
| Issued Date: | September 08, 2006 |
| File Close Date: | September 21, 2010 |
Associated Properties
| Address | Zone | More |
|---|---|---|
| 433 POPLAR STREET | R5 | Property Report |
Process Steps
| Task | Status |
|---|---|
|
FOOTING / FORMS
Inspection of forms prior to any concrete being poured |
CANCELLED |
|
FOOTING / FORMS
Inspection of forms prior to any concrete being poured |
PASSED |
|
PERIMETER DRAIN
For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering |
PASSED |
|
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
CANCELLED |
|
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval |
PASSED |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
PASSED |
|
FINAL
Final approval as per requirements on plans. |
CANCELLED |
|
FINAL
Final approval as per requirements on plans. |
FAILED |
|
FINAL
Final approval as per requirements on plans. |
FAILED |
|
FINAL
Final approval as per requirements on plans. |
PASSED
2010-09-21 |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

View in Google Earth (KML)