BP110352 - 1809 Bowen -- Drawing FP Scanned/Attached
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP110352 - 1809 Bowen -- Drawing FP Scanned/Attached | |
|---|---|
| Neighbourhood: | Northfield |
| Street Address: | 1809 Bowen -- Drawing FP Scanned/Attached |
| Type of Application: | Commercial / Multi / Industrial |
| File Number: | BP110352 |
| Date Application Submitted: | June 15, 2006 |
| Application Description: |
VI Honda- x reference BP 110771 for the foundation and concrete block walls. Also xreference BP 110321 for the demolition and bp110637. Construction of building for VI Honda, old building is demolished under previous permit bp110321 except for the rear portion of the building. Foundation for new construction and concrete wall under bp110771. This permit includes new construction. Building classification, 3.2.2.72 (Most restrictive), Building area 1062m2, installing sprinklers throughout and fire alarm system. Combustible construction permitted, includes two major occupancies Group E (Showroom), and Group F2 (Repair garage) at rear divided by 2hr FRR/FS in accordance 3.3. Right side (North) exposed wall face requires 2 hr. FRR/with non-combustible construction and non-combustible cladding. Rear (West) 2hr FRR with non-combustible cladding |
| Application Status: | COMPLETED |
| Permit Value: | $700,000.00 |
| Issued Date: | January 29, 2007 |
| File Close Date: | June 26, 2007 |
Associated Properties
| Address | Zone | More |
|---|---|---|
| 1809 BOWEN ROAD | COR3 | Property Report |
Process Steps
| Task | Status |
|---|---|
|
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
|
STORM CONNECTION
Pipe and connection must be visible for inspection. |
PARTIAL |
|
SANITARY CONNECTION
Pipe and connection must be visible for inspection. |
PARTIAL |
|
WATER CONNECTION
Pipe and connection must be visible for inspection. |
PARTIAL |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
|
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
|
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PARTIAL |
|
PLUMBING FINAL-OLD
All fixtures must be in place. |
PARTIAL |
| OCCUPANCY-OLD | CANCELLED |
| OCCUPANCY-OLD | FAILED |
| OCCUPANCY-OLD | FAILED |
| OCCUPANCY-OLD |
PASSED
2007-06-26 |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

View in Google Earth (KML)