BP110201 - 980 Malaspina crescent
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP110201 - 980 Malaspina crescent | |
|---|---|
| Neighbourhood: | Newcastle/Brechin |
| Street Address: | 980 Malaspina crescent |
| Type of Application: | Garage / Carport Permit |
| File Number: | BP110201 |
| Date Application Submitted: | May 09, 2006 |
| Application Description: |
Demolish existing carport. Add approx 21 x 28 ft garage addition and 6 x 10 ft foyer addition at front of existing single family dwelling. Interior renovations to main and lower floor (powder room addition and ensuite renovation) BOV00307 Nov 21, 2008 - See events TW BCLS Certificate of Location attached db |
| Application Status: | COMPLETED |
| Permit Value: | $65,000.00 |
| Building Area: |
6.13 M2 65.98 ft2 |
| Issued Date: | May 26, 2006 |
| File Close Date: | October 09, 2009 |
Associated Properties
| Address | Zone | More |
|---|---|---|
| 980 MALASPINA CRESCENT | R5 | Property Report |
Process Steps
| Task | Status |
|---|---|
|
LATERAL BRACING & SHEATHING
All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors. |
COMPLETED |
|
FOOTING/FORMS
Inspection of forms prior to any cement being poured . For footing inspection, forms must be complete and approved plans (complete with City Stamp) must be onsite. |
PARTIAL |
|
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
|
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible. |
FAILED |
|
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible. |
PASSED |
|
ROUGH IN PLUMBING
Pipe and connection must be visable for inspection. |
PARTIAL |
|
ROUGH IN PLUMBING
Pipe and connection must be visable for inspection. |
PARTIAL |
|
FRAMING
Rough-in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
|
FRAMING
Rough-in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
|
FINAL-OLD
Final Approval as per requested on plans. |
FAILED |
|
FINAL-OLD
Final Approval as per requested on plans. |
FAILED |
|
FINAL-OLD
Final Approval as per requested on plans. |
PASSED
2009-10-09 |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

View in Google Earth (KML)