BP110160 - 4750 Rutherford Road
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP110160 - 4750 Rutherford Road | |
|---|---|
| Neighbourhood: | Rutherford |
| Street Address: | 4750 Rutherford Road |
| Type of Application: | Commercial / Multi-Res Alteration |
| File Number: | BP110160 |
| Date Application Submitted: | May 02, 2006 |
| Application Description: |
Foundation permit only construction shall not proceed beyond the foundation stage until the permit for the remainder is issued. (Bp110247). Xreference BP110090 for the demolition. 3.2.2.57, Group E, Non-combustible Construction, Sprinklered and Fire Alarm Systems. |
| Application Status: | COMPLETED |
| Permit Value: | $970,000.00 |
| Builder: | WINDLEY CONTRACTING LTD |
| Issued Date: | May 23, 2006 |
| File Close Date: | March 09, 2007 |
Process Steps
| Task | Status |
|---|---|
|
FOOTING/FORMS
Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
|
FOOTING/FORMS
Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
|
FOOTING/FORMS
Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
|
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PARTIAL |
|
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PARTIAL |
|
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PARTIAL |
|
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
|
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
|
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
|
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
|
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
|
FINAL-OLD
Final approval as per requirements on plans. |
PASSED
2007-03-09 |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

View in Google Earth (KML)