BP109898 - 4700 Hammond Bay

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP109898 - 4700 Hammond Bay
Neighbourhood: North Slope    
Street Address: 4700 Hammond Bay
Type of Application: Commercial / Multi / Industrial
File Number: BP109898
Date Application Submitted: February 24, 2006
Application Description: Pipers Pub
3.2.2.27, Group A, Division 2, 2 storeys, sprinklers, fire alarm, combustible construction, 1st storey = 529.53m2 , 2nd storey = 88.26m2 , 0 hr. floor assemblies, single exit from 2nd storey 45min min. FRR/FS. min (3.4.4.1) , exposed building face East exterior wall 45 min FRR. Occupant Load = 140 patrons. 35 patrons patio
Accessible to persons with disabilities . Main entrance to be provided with an automatic door opener. Accessible unisex restroom. Female restroom = 4 water closets, male restroom =1 water closet, 3 urinals.

Revised occupant load on October 17, 2006 to 175-occupant load. Subject to civil drawings submitted to accommodate the 83 parking spots, See attached letter.
Forwarded civil to engineering on Oct 19,2006

Physical File Scanned + attached June 25, 2008 db
Application Status: COMPLETED
Permit Value: $800,000.00
Builder: WINDLEY CONTRACTING LTD
Issued Date: July 06, 2006
File Close Date: May 05, 2008

Associated Properties

Address Zone More
4700 HAMMOND BAY ROAD CC1 Property Report

Process Steps

Task Status
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete.

CANCELLED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

CANCELLED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PARTIAL
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PASSED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

CANCELLED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

CANCELLED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PASSED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PASSED
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

PARTIAL
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

PARTIAL
PLUMBING FINAL-OLD

All fixtures must be in place.

PARTIAL
PLUMBING FINAL-OLD

All fixtures must be in place.

PARTIAL
OCCUPANCY-OLD FAILED
OCCUPANCY-OLD PARTIAL
OCCUPANCY-OLD FAILED
OCCUPANCY-OLD PASSED

2008-05-05

FINAL-OLD

Final approval as per requirements on plans.

PARTIAL
Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.