BP109676 - 1650 Waddington -- Drawings Scanned/Attached
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP109676 - 1650 Waddington -- Drawings Scanned/Attached | |
|---|---|
| Neighbourhood: | Townsite |
| Street Address: | 1650 Waddington -- Drawings Scanned/Attached |
| Type of Application: | Commercial / Multi / Industrial |
| File Number: | BP109676 |
| Date Application Submitted: | January 04, 2006 |
| Application Description: |
First Baptist Church - FOUNDATION ONLY for 369.5m2 addition to 1170m2 existing church. No work permitted beyond the perimeter drain installation and underslab plumbing without issuance of BP109675. Existing building + addition will be 1539.5m2. New classification for building under BCBC 1998 will be 3.2.2.26. Group A-2, sprinklered, 2 storey, <2400m2, combustible or non-combustible, 45 minute floors and supports. |
| Application Status: | COMPLETED |
| Permit Value: | $180,000.00 |
| Builder: | R W (BOB) WALL CONTRACTING LTD |
| Issued Date: | March 02, 2006 |
| File Close Date: | January 31, 2007 |
Associated Properties
| Address | Zone | More |
|---|---|---|
| 1650 WADDINGTON ROAD | CS1 | Property Report |
Process Steps
| Task | Status |
|---|---|
|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
|
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
|
FIRELINE
Fireline for the sprinkler system must be complete and visable for inspection. |
FAILED |
|
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
|
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
|
WATER CONNECTION
Pipe and connection must be visible for inspection. |
FAILED |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
|
FINAL-OLD
Final approval as per requirements on plans. |
PASSED
2007-01-31 |
|
FINAL-OLD
Final approval as per requirements on plans. |
CANCELLED |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

View in Google Earth (KML)