BP109675 - 1650 Waddington Road -- Drawings Scanned/Attached
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP109675 - 1650 Waddington Road -- Drawings Scanned/Attached | |
|---|---|
| Neighbourhood: | Townsite |
| Street Address: | 1650 Waddington Road -- Drawings Scanned/Attached |
| Type of Application: | Commercial / Multi / Industrial |
| File Number: | BP109675 |
| Date Application Submitted: | January 04, 2006 |
| Application Description: |
First Baptist Church - 369.5m2 main floor and 125.8m2 second floor addition to 1314.3m2 existing church. Foundation under BP109675. Existing building + addition will be 1683.7m2. New classification for building under BCBC 1998 will be 3.2.2.26. Group A-2, sprinklered with fire alarm, 2 storey, <2400m2, combustible or non-combustible construction permitted, 45 minute floors and supports. |
| Application Status: | COMPLETED |
| Permit Value: | $900,000.00 |
| Builder: | RW (BOB) WALL LTD |
| Issued Date: | June 27, 2006 |
| File Close Date: | January 31, 2007 |
Associated Properties
| Address | Zone | More |
|---|---|---|
| 1650 WADDINGTON ROAD | CS1 | Property Report |
Process Steps
| Task | Status |
|---|---|
|
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
|
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
|
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
|
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
|
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
|
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
|
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PARTIAL |
|
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PASSED |
|
PLUMBING FINAL-OLD
All fixtures must be in place. |
PARTIAL |
|
PLUMBING FINAL-OLD
All fixtures must be in place. |
PARTIAL |
|
PLUMBING FINAL-OLD
All fixtures must be in place. |
PASSED |
|
FINAL-OLD
Final approval as per requirements on plans. |
CANCELLED |
|
FINAL-OLD
Final approval as per requirements on plans. |
PASSED
2007-01-31 |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

View in Google Earth (KML)