BP109449 - 860 Beach Drive
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP109449 - 860 Beach Drive | |
|---|---|
| Neighbourhood: | Newcastle/Brechin |
| Street Address: | 860 Beach Drive |
| Type of Application: | Single / Two Family Dwelling |
| File Number: | BP109449 |
| Date Application Submitted: | October 24, 2005 |
| Application Description: |
6.5 x 43 ft kitchen/bedroom addition at rear, and 20 x 20 ft deck addition on right side of existing single family dwelling. Revision Sept. 7, 2006 -Changing deck design and adding stairs/retaining walls. AG Revision submitted Nov.17, 2008 1) Changing deck to storage room roof 2) Changing from post & beam to framed walls 3) Removing door onto deck 4) Enclosing for storage space AG Physical file scanned and attached Dec 10/08 |
| Application Status: | COMPLETED |
| Permit Value: | $19,000.00 |
| Building Area: |
26.10 M2 280.94 ft2 |
| Issued Date: | November 21, 2005 |
| File Close Date: | November 21, 2008 |
Associated Properties
| Address | Zone | More |
|---|---|---|
| 860 BEACH DRIVE | R1 | Property Report |
Process Steps
| Task | Status |
|---|---|
|
FOOTING / FORMS
Inspection of forms prior to any concrete being poured |
PASSED |
|
FOOTING / FORMS
Inspection of forms prior to any concrete being poured |
PASSED |
|
PERIMETER DRAIN
For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering |
PASSED |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping |
PARTIAL |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping |
PARTIAL |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping |
PASSED |
|
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval |
FAILED |
|
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval |
PASSED |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
CANCELLED |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
PASSED |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
FAILED |
|
FINAL
Final approval as per requirements on plans. |
PASSED
2008-11-21 |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

View in Google Earth (KML)