Date Application Submitted: October 05, 2005
Application Description: Marine Vista - 485m2, 23 unit, eight storey apartment. 3.2.6 requirements for high buildings applies, 1 hr fire separation between suites and between suites and corridor and storage rooms, 2 hr fire separation for exit stairs, elevator and vestibule, 1.5 hr FRR/FS between storage garage and floor above. Code compliance and equivalency report by GHL for standpipe in scissor exit stairs. Cross-reference BP109390 for foundation.

Building 8 storey + 1 storey below grade parking, 23 unit Group C occupancy with Group F-3 storage garage, 3.2.2.42. non-combustible, sprinklered "high building" with fire alarm, 2 hr floor assemblies, 1 hr FRR between suites and between corridor.

Physical File Scanned + attached Nov 27, 2008 db
Application Status: COMPLETED
Permit Value: $3,986,400.00
Builder: TOTAL ENVIRONMENTS LTD
Issued Date: October 27, 2006
File Close Date: July 03, 2008

Associated Properties

Address Zone More
225 ROSEHILL STREET R8 Property Report

Process Steps

Task Status
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

FAILED
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

CANCELLED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
MONITORING FIELD REVIEW

A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional.

PARTIAL
MONITORING FIELD REVIEW

A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional.

PARTIAL
MONITORING FIELD REVIEW

A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional.

PARTIAL
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

PARTIAL
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

PARTIAL
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

PASSED
PLUMBING FINAL-OLD

All fixtures must be in place.

PASSED
OCCUPANCY-OLD PARTIAL
OCCUPANCY-OLD PARTIAL
OCCUPANCY-OLD PASSED

2008-07-04

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.