BP109070 - 475 Eighth Street (Lot B)
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP109070 - 475 Eighth Street (Lot B) | |
|---|---|
| Neighbourhood: | Harewood |
| Street Address: | 475 Eighth Street (Lot B) |
| Type of Application: | Single / Two Family Dwelling |
| File Number: | BP109070 |
| Date Application Submitted: | July 14, 2005 |
| Application Description: |
Two-storey SFD (second dwelling on the parent parcel) on slab with built in double garage and bonus room above. BOV00257 passed for shop area. Added five plumbing fixtures to garage Nov, 30, 05 See BP107735 for servicing and access permit fees. Sept 22 / 05 Revision - larger rear deck - eng. floor - new footing. cb Sept 2007 Lots changed from B to D |
| Application Status: | COMPLETED |
| Permit Value: | $233,000.00 |
| Building Area: |
291.89 M2 3,141.87 ft2 |
| Issued Date: | August 31, 2005 |
| File Close Date: | March 14, 2006 |
Associated Properties
| Address | Zone | More |
|---|---|---|
| 475 EIGHTH STREET | R1 | Property Report |
Process Steps
| Task | Status |
|---|---|
|
FOOTING / FORMS
Inspection of forms prior to any concrete being poured |
PASSED |
|
PERIMETER DRAIN
For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering |
PASSED |
|
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible |
FAILED |
|
STORM CONNECTION
Pipe and Connection must be visible for inspection |
PASSED |
|
SANITARY CONNECTION
Pipe and Connection must be visible for inspection |
PASSED |
|
WATER CONNECTION
Pipe and Connection must be visable for inspection |
PASSED |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping |
PARTIAL |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping |
FAILED |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping |
FAILED |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping |
PASSED |
|
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval |
FAILED |
|
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval |
FAILED |
|
OCCUPANCY-OLD
Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish |
FAILED |
|
OCCUPANCY-OLD
Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish |
FAILED |
|
OCCUPANCY-OLD
Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish |
PASSED
2006-03-14 |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

View in Google Earth (KML)