Date Application Submitted: July 15, 2005
Application Description: Revised on July 6, 2006, added 2 floors, 8 units, Total units in building 169 units. Changed the building height to 22 storeys (by code).

Pacifica - 161 units Multi family development - 20 Storey High Rise by code Group C and F3 occupancy, Building Classification 3.2.2.42- non combustible construction, sprinklered, fire alarm, floor assemblies 2 hr FS/FRR, Public corridor 1 hrs FS/FRR, Suite separation 1 hr FRR/FS, Roof assemblies supporting occupancy 2 hr FS/FRR, floor assemblies, (2 level dwelling units 1 hr FRR for floor assemblies and roof assemblies)
All load bearing support to have FRR of the supported assembly. Exits 2 hrs FS/FRR. One exit through lobby. Equivalencies for fire department access and protection of exits. See code compliance report.
Total Area =26,650 m2 , (parking garage 7992 m2, condos =18,658 m2 )

RENEWED PERMIT FOR TWO YEARS EXPIRY DATE DEC 13, 2009
Application Status: COMPLETED
Permit Value: $28,000,000.00
Builder: NANAIMO HARBOUR FRONT DEVELOPMENT CORPORATION
Issued Date: December 13, 2005
File Close Date: July 19, 2010

Associated Properties

Address Zone More
403   38 FRONT STREET DT5 Property Report
404   38 FRONT STREET DT5 Property Report
405   38 FRONT STREET DT5 Property Report
406   38 FRONT STREET DT5 Property Report
407   38 FRONT STREET DT5 Property Report
408   38 FRONT STREET DT5 Property Report
409   38 FRONT STREET DT5 Property Report
510   38 FRONT STREET DT5 Property Report
511   38 FRONT STREET DT5 Property Report
512   38 FRONT STREET DT5 Property Report
501   38 FRONT STREET DT5 Property Report
502   38 FRONT STREET DT5 Property Report
503   38 FRONT STREET DT5 Property Report
504   38 FRONT STREET DT5 Property Report
505   38 FRONT STREET DT5 Property Report
506   38 FRONT STREET DT5 Property Report
507   38 FRONT STREET DT5 Property Report
508   38 FRONT STREET DT5 Property Report
509   38 FRONT STREET DT5 Property Report
610   38 FRONT STREET DT5 Property Report
611   38 FRONT STREET DT5 Property Report
612   38 FRONT STREET DT5 Property Report
601   38 FRONT STREET DT5 Property Report
602   38 FRONT STREET DT5 Property Report
603   38 FRONT STREET DT5 Property Report
604   38 FRONT STREET DT5 Property Report
605   38 FRONT STREET DT5 Property Report
606   38 FRONT STREET DT5 Property Report
607   38 FRONT STREET DT5 Property Report
608   38 FRONT STREET DT5 Property Report
609   38 FRONT STREET DT5 Property Report
710   38 FRONT STREET DT5 Property Report
711   38 FRONT STREET DT5 Property Report
712   38 FRONT STREET DT5 Property Report
701   38 FRONT STREET DT5 Property Report
702   38 FRONT STREET DT5 Property Report
703   38 FRONT STREET DT5 Property Report
704   38 FRONT STREET DT5 Property Report
705   38 FRONT STREET DT5 Property Report
706   38 FRONT STREET DT5 Property Report
707   38 FRONT STREET DT5 Property Report
708   38 FRONT STREET DT5 Property Report
709   38 FRONT STREET DT5 Property Report
805   38 FRONT STREET DT5 Property Report
806   38 FRONT STREET DT5 Property Report
801   38 FRONT STREET DT5 Property Report
802   38 FRONT STREET DT5 Property Report
803   38 FRONT STREET DT5 Property Report
804   38 FRONT STREET DT5 Property Report
905   38 FRONT STREET DT5 Property Report
906   38 FRONT STREET DT5 Property Report
901   38 FRONT STREET DT5 Property Report
902   38 FRONT STREET DT5 Property Report
903   38 FRONT STREET DT5 Property Report
904   38 FRONT STREET DT5 Property Report
1005   38 FRONT STREET DT5 Property Report
1006   38 FRONT STREET DT5 Property Report
1001   38 FRONT STREET DT5 Property Report
1002   38 FRONT STREET DT5 Property Report
1003   38 FRONT STREET DT5 Property Report
1004   38 FRONT STREET DT5 Property Report
1105   38 FRONT STREET DT5 Property Report
1106   38 FRONT STREET DT5 Property Report
1101   38 FRONT STREET DT5 Property Report
1102   38 FRONT STREET DT5 Property Report
1103   38 FRONT STREET DT5 Property Report
1104   38 FRONT STREET DT5 Property Report
1204   38 FRONT STREET DT5 Property Report
1201   38 FRONT STREET DT5 Property Report
1202   38 FRONT STREET DT5 Property Report
1203   38 FRONT STREET DT5 Property Report
1304   38 FRONT STREET DT5 Property Report
1301   38 FRONT STREET DT5 Property Report
1302   38 FRONT STREET DT5 Property Report
1303   38 FRONT STREET DT5 Property Report
1404   38 FRONT STREET DT5 Property Report
1401   38 FRONT STREET DT5 Property Report
1402   38 FRONT STREET DT5 Property Report
1403   38 FRONT STREET DT5 Property Report
1504   38 FRONT STREET DT5 Property Report
1501   38 FRONT STREET DT5 Property Report
1502   38 FRONT STREET DT5 Property Report
1503   38 FRONT STREET DT5 Property Report
1604   38 FRONT STREET DT5 Property Report
1601   38 FRONT STREET DT5 Property Report
1602   38 FRONT STREET DT5 Property Report
1603   38 FRONT STREET DT5 Property Report
1704   38 FRONT STREET DT5 Property Report
1701   38 FRONT STREET DT5 Property Report
1702   38 FRONT STREET DT5 Property Report
1703   38 FRONT STREET DT5 Property Report
1804   38 FRONT STREET DT5 Property Report
1801   38 FRONT STREET DT5 Property Report
1802   38 FRONT STREET DT5 Property Report
1803   38 FRONT STREET DT5 Property Report
A   38 FRONT STREET DT5 Property Report
TH13   38 FRONT STREET DT5 Property Report
TH12   38 FRONT STREET DT5 Property Report
TH11   38 FRONT STREET DT5 Property Report
TH10   38 FRONT STREET DT5 Property Report
TH09   38 FRONT STREET DT5 Property Report
TH08   38 FRONT STREET DT5 Property Report
TH07   38 FRONT STREET DT5 Property Report
TH06   38 FRONT STREET DT5 Property Report
TH05   38 FRONT STREET DT5 Property Report
TH04   38 FRONT STREET DT5 Property Report
TH03   38 FRONT STREET DT5 Property Report
TH02   38 FRONT STREET DT5 Property Report
TH01   38 FRONT STREET DT5 Property Report
TH26   38 FRONT STREET DT5 Property Report
TH25   38 FRONT STREET DT5 Property Report
TH24   38 FRONT STREET DT5 Property Report
TH23   38 FRONT STREET DT5 Property Report
TH22   38 FRONT STREET DT5 Property Report
TH21   38 FRONT STREET DT5 Property Report
TH20   38 FRONT STREET DT5 Property Report
TH19   38 FRONT STREET DT5 Property Report
TH18   38 FRONT STREET DT5 Property Report
TH17   38 FRONT STREET DT5 Property Report
TH16   38 FRONT STREET DT5 Property Report
TH15   38 FRONT STREET DT5 Property Report
TH14   38 FRONT STREET DT5 Property Report
CY03   38 FRONT STREET DT5 Property Report
CY04   38 FRONT STREET DT5 Property Report
CY01   38 FRONT STREET DT5 Property Report
CY02   38 FRONT STREET DT5 Property Report
PL03   38 FRONT STREET DT5 Property Report
PL04   38 FRONT STREET DT5 Property Report
PL05   38 FRONT STREET DT5 Property Report
PL01   38 FRONT STREET DT5 Property Report
PL02   38 FRONT STREET DT5 Property Report
109   38 FRONT STREET DT5 Property Report
110   38 FRONT STREET DT5 Property Report
101   38 FRONT STREET DT5 Property Report
102   38 FRONT STREET DT5 Property Report
103   38 FRONT STREET DT5 Property Report
104   38 FRONT STREET DT5 Property Report
105   38 FRONT STREET DT5 Property Report
106   38 FRONT STREET DT5 Property Report
107   38 FRONT STREET DT5 Property Report
108   38 FRONT STREET DT5 Property Report
210   38 FRONT STREET DT5 Property Report
211   38 FRONT STREET DT5 Property Report
212   38 FRONT STREET DT5 Property Report
201   38 FRONT STREET DT5 Property Report
202   38 FRONT STREET DT5 Property Report
203   38 FRONT STREET DT5 Property Report
204   38 FRONT STREET DT5 Property Report
205   38 FRONT STREET DT5 Property Report
206   38 FRONT STREET DT5 Property Report
207   38 FRONT STREET DT5 Property Report
208   38 FRONT STREET DT5 Property Report
209   38 FRONT STREET DT5 Property Report
310   38 FRONT STREET DT5 Property Report
311   38 FRONT STREET DT5 Property Report
312   38 FRONT STREET DT5 Property Report
301   38 FRONT STREET DT5 Property Report
302   38 FRONT STREET DT5 Property Report
303   38 FRONT STREET DT5 Property Report
304   38 FRONT STREET DT5 Property Report
305   38 FRONT STREET DT5 Property Report
306   38 FRONT STREET DT5 Property Report
307   38 FRONT STREET DT5 Property Report
308   38 FRONT STREET DT5 Property Report
309   38 FRONT STREET DT5 Property Report
410   38 FRONT STREET DT5 Property Report
411   38 FRONT STREET DT5 Property Report
412   38 FRONT STREET DT5 Property Report
401   38 FRONT STREET DT5 Property Report
402   38 FRONT STREET DT5 Property Report

Process Steps

Task Status
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PARTIAL
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PARTIAL
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PARTIAL
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PARTIAL
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

CANCELLED
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PARTIAL
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PARTIAL
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

CANCELLED
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PARTIAL
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PARTIAL
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PARTIAL
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PARTIAL
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PARTIAL
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PARTIAL
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PARTIAL
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PARTIAL
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PARTIAL
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PARTIAL
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PARTIAL
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PARTIAL
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

FAILED
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PARTIAL
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PARTIAL
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PARTIAL
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PARTIAL
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete.

FAILED
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete.

PARTIAL
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete.

PARTIAL
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete.

PARTIAL
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete.

PARTIAL
SANITARY CONNECTION

Pipe and connection must be visible for inspection.

CANCELLED
WATER CONNECTION

Pipe and connection must be visible for inspection.

PARTIAL
WATER CONNECTION

Pipe and connection must be visible for inspection.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PARTIAL
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PARTIAL
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

CANCELLED
MONITORING FIELD REVIEW

A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional.

PARTIAL
MONITORING FIELD REVIEW

A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional.

PARTIAL
MONITORING FIELD REVIEW

A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional.

CANCELLED
MONITORING FIELD REVIEW

A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional.

PARTIAL
MONITORING FIELD REVIEW

A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional.

PARTIAL
MONITORING FIELD REVIEW

A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional.

CANCELLED
MONITORING FIELD REVIEW

A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional.

PARTIAL
MONITORING FIELD REVIEW

A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional.

CANCELLED
MONITORING FIELD REVIEW

A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional.

PARTIAL
MONITORING FIELD REVIEW

A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional.

PARTIAL
MONITORING FIELD REVIEW

A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional.

PARTIAL
MONITORING FIELD REVIEW

A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional.

PASSED
PLUMBING FINAL-OLD

All fixtures must be in place.

PARTIAL
PLUMBING FINAL-OLD

All fixtures must be in place.

PARTIAL
OCCUPANCY-OLD PARTIAL
OCCUPANCY-OLD FAILED
OCCUPANCY-OLD FAILED
OCCUPANCY-OLD FAILED
OCCUPANCY-OLD FAILED
OCCUPANCY-OLD PARTIAL
OCCUPANCY-OLD FAILED
OCCUPANCY-OLD PARTIAL
OCCUPANCY-OLD PASSED

2010-07-19

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.