| Application Description: |
Locate a one-storey sfd, on new a foundation with a partly finished basement including a detached double garage. Revision - Oct 05/05 - Windows and location revised on right elevation. Point loaded lintel in basement at right rear. DG Added bar sink, March 23, 2007 LK Mar 2009 - File is at Tom W's desk. See events. Physical File Scanned + attached Jun 22, 2009 db |
| Application Status: | COMPLETED |
| Permit Value: | $42,000.00 |
| Building Area: |
210.00 M2 2,260.42 ft2 |
| Issued Date: | July 11, 2005 |
| File Close Date: | April 21, 2009 |
Associated Properties
| Address | Zone | More |
|---|---|---|
| 25 GILLESPIE STREET | R5 | Property Report |
Process Steps
| Task | Status |
|---|---|
|
FOOTING/FORMS
Inspection of Forms prior to any cement being poured. For Footing inspection, forms must be complete and approved plans (complete with City Stamp) must be onsite. |
PASSED |
|
PERIMETER DRAIN
For Perimeter Drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
|
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible. |
CANCELLED |
|
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible. |
PASSED |
|
UNDERSLAB INSULATION
Inspection required prior to placing slab concete. |
PASSED |
|
STORM CONNECTION
Pipe connection must be visible for inspection. |
CANCELLED |
|
SANITARY CONNECTION
Pipe Connection must be visible for inspection. |
PARTIAL |
|
WATER CONNECTION
Pipe Connection must be visible for inspection. |
PARTIAL |
|
CHIMMEY
To be inspected while all components and clearances are visible. |
PARTIAL |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
|
LATERAL BRACING & SHEATHING
All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors. |
PARTIAL |
|
LATERAL BRACING & SHEATHING
All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors. |
PASSED |
|
OCCUPANCY-OLD
Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish |
PASSED
2009-04-21 |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

View in Google Earth (KML)