BP108723 - 2630 Labieux -- Drawings Scanned/Attached

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP108723 - 2630 Labieux -- Drawings Scanned/Attached
Neighbourhood: Diver Lake    
Street Address: 2630 Labieux -- Drawings Scanned/Attached
Type of Application: Commercial / Multi / Industrial
File Number: BP108723
Date Application Submitted: May 04, 2005
Application Description: Renovate main floor of front left wing to accommodate new bathrooms and three patient rooms. Fire separation only for 1100mm width Corridor, self closing devices on storage closet, and door to lobby, 1050mm doors servicing patients sleeping rooms 3.4.3.1. interconnected smoke alarms.

3.2.2.40
Existing B2 occupancy, Building area 925m2 sprinklered, fire alarm, combustible, 45min FRR/FS for floor assemblies and load bearing supports. 2 storey
Application Status: COMPLETED
Permit Value: $50,000.00
Issued Date: July 04, 2005
File Close Date: May 11, 2007

Associated Properties

Address Zone More
2630 LABIEUX ROAD CS1 Property Report

Process Steps

Task Status
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PASSED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PASSED
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PARTIAL
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PASSED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PASSED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PASSED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

SCHEDULED
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

PARTIAL
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

PASSED
PLUMBING FINAL-OLD

All fixtures must be in place.

PARTIAL
PLUMBING FINAL-OLD

All fixtures must be in place.

PASSED
FINAL-OLD

Final approval as per requirements on plans.

FAILED
FINAL-OLD

Final approval as per requirements on plans.

PASSED

2007-05-11

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.