BP108574 - 120 Commercial Street
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP108574 - 120 Commercial Street | |
|---|---|
| Neighbourhood: | Downtown/Old City |
| Street Address: | 120 Commercial Street |
| Type of Application: | Commercial / Multi / Industrial |
| File Number: | BP108574 |
| Date Application Submitted: | April 04, 2005 |
| Application Description: |
Heritage Building - Gusola Block - SEE FOLDER COMMENTS Change of Existing use of 211m2 (building footprint area) two storey building with basement, total area = 621.75 m2, combustible, sprinklered, fire alarm. Part 3 building. 3.2.2.25. Roof assembly 45 min. FRR/FS. 2nd storey, Group C, Residential, 3 dwelling units with min. 45 min. FRR/FS 50 STM between units and the public corridor. Single exit from corridor by Equivalency C. 1st storey Group E or Group A. Future permit for the tenants on the first storey and in the basement is required. Providing 2 hr FRR/FS floor assembly including 2 hr FRR for loadbearing supports between 1st and 2nd storey and basement . Providing 2 hr FRR/FS for exit between 1st and 2nd storey. Exit exposure protection via water curtain located at the exposing openings, provided per Equivalency A. for exits from the first storey. Basement Group E, Retail, single exit by Equivalency B. Accessibility for persons with disabilities for main floor only. |
| Application Status: | COMPLETED |
| Permit Value: | $700,000.00 |
| Builder: | TECTONICA MANAGEMENT INC |
| Issued Date: | December 22, 2005 |
| File Close Date: | July 20, 2007 |
Associated Properties
| Address | Zone | More |
|---|---|---|
| 120 COMMERCIAL STREET | DT1 | Property Report |
Process Steps
| Task | Status |
|---|---|
|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
|
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
|
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
FAILED |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
CANCELLED |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
|
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
|
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
|
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
CANCELLED |
|
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
CANCELLED |
|
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
|
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
|
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
FAILED |
|
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PASSED |
|
PLUMBING FINAL-OLD
All fixtures must be in place. |
PARTIAL |
|
PLUMBING FINAL-OLD
All fixtures must be in place. |
PASSED |
| OCCUPANCY-OLD | CANCELLED |
| OCCUPANCY-OLD | PARTIAL |
| OCCUPANCY-OLD | FAILED |
| OCCUPANCY-OLD |
PASSED
2007-07-20 |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

View in Google Earth (KML)