BP108450 - 2300 Northfield -- Drawings Scanned/Attached

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP108450 - 2300 Northfield -- Drawings Scanned/Attached
Neighbourhood: Diver Lake    
Street Address: 2300 Northfield -- Drawings Scanned/Attached
Type of Application: Commercial / Multi / Industrial
File Number: BP108450
Date Application Submitted: February 25, 2005
Application Description: 284 m2 convenience store / gas bar for Northfield ESSO and 10.67 x 20.73 metre detached gas pump canopy.
284m2 "E" occupancy, Part 9 combustible building, sprinklered by bylaw.

July 6, 2005 Food preparation area added, plans approved by Department of Health. Hood design plans by Undershute Engineering for donut machine approved by Fire Department. Not considered a restaurant, 10 or less seats. VS
Application Status: COMPLETED
Permit Value: $388,000.00
Builder: 706673 BC LTD
Issued Date: April 27, 2005
File Close Date: December 20, 2005

Process Steps

Task Status
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PASSED
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PASSED
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PARTIAL
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PASSED
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PARTIAL
STORM CONNECTION

Pipe and connection must be visible for inspection.

PARTIAL
SANITARY CONNECTION

Pipe and connection must be visible for inspection.

PARTIAL
WATER CONNECTION

Pipe and connection must be visible for inspection.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

FAILED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

FAILED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

FAILED
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

PASSED
PLUMBING FINAL-OLD

All fixtures must be in place.

FAILED
PLUMBING FINAL-OLD

All fixtures must be in place.

PASSED
FINAL-OLD

Final approval as per requirements on plans.

FAILED
FINAL-OLD

Final approval as per requirements on plans.

PASSED

2005-12-20

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.