BP107745 - 6520 Ptarmigan Way - DRAWINGS ATTACHED
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP107745 - 6520 Ptarmigan Way - DRAWINGS ATTACHED | |
|---|---|
| Neighbourhood: | Dover |
| Street Address: | 6520 Ptarmigan Way - DRAWINGS ATTACHED |
| Type of Application: | Single / Two Family Dwelling |
| File Number: | BP107745 |
| Date Application Submitted: | July 26, 2004 |
| Application Description: |
One story single family dwelling, partially finished daylight basement (hallway, two bedrooms, family rm, laundry & bathroom), slab, attached garage. Nov. 12, 04 Washer and dryer rough-in added to main floor mudroom. Letter of Intent signed. Plumbing fee paid. VS |
| Application Status: | COMPLETED |
| Permit Value: | $211,995.51 |
| Building Area: |
304.46 M2 3,277.18 ft2 |
| Builder: | GAUTHIER DEVELOPMENTS LTD |
| Issued Date: | September 03, 2004 |
| File Close Date: | April 05, 2005 |
Associated Properties
| Address | Zone | More |
|---|---|---|
| 6520 PTARMIGAN WAY | R1 | Property Report |
Process Steps
| Task | Status |
|---|---|
|
FOOTING / FORMS
Inspection of forms prior to any concrete being poured |
PASSED |
|
PERIMETER DRAIN
For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering |
PASSED |
|
PERIMETER DRAIN
For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering |
PASSED |
|
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible |
PASSED |
|
STORM CONNECTION
Pipe and Connection must be visible for inspection |
PASSED |
|
SANITARY CONNECTION
Pipe and Connection must be visible for inspection |
FAILED |
|
SANITARY CONNECTION
Pipe and Connection must be visible for inspection |
PASSED |
|
WATER CONNECTION
Pipe and Connection must be visable for inspection |
PASSED |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping |
PARTIAL |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping |
PASSED |
|
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval |
PARTIAL |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
PARTIAL |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
PASSED |
|
OCCUPANCY-OLD
Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish |
FAILED |
|
OCCUPANCY-OLD
Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish |
PASSED
2005-04-05 |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

View in Google Earth (KML)