BP107507 - 6175 McGirr - SCANNED
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP107507 - 6175 McGirr - SCANNED | |
|---|---|
| Neighbourhood: | Dover |
| Street Address: | 6175 McGirr - SCANNED |
| Type of Application: | Commercial / Multi / Industrial |
| File Number: | BP107507 |
| Date Application Submitted: | May 27, 2004 |
| Application Description: |
McGirr Sports Field (Field House) Part 3 Building, Sprinklered, Fire Alarm, Building area: 2754 (255.8m2), Building Classification: 3.2.2.27. One Storey. No rating required for the roof deck.Main Floor has concession, washroom, change rooms, office, storage and official rooms. The perimeter of the roof deck is for viewing with non-fixed seating. Occupant Load for the roof deck = 139.35m2/0.95 = 146 persons, plan showing table layout attached to plans. 2 exits required from deck. Door at the bottom of the stairs to be secured open when roof deck is used. Signage on door may be required by the inspector. Accessible toilet room on main floor with accessible shower in the first aid room/accessible toilet room. Accessible toilet compartment in the male and female washroom. |
| Application Status: | COMPLETED |
| Permit Value: | $400,000.00 |
| Builder: | CITY OF NANAIMO |
| Issued Date: | October 26, 2004 |
| File Close Date: | May 25, 2005 |
Associated Properties
| Address | Zone | More |
|---|---|---|
| 6175 MCGIRR ROAD | PRC3 | Property Report |
Process Steps
| Task | Status |
|---|---|
|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
|
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
|
FIRELINE
Fireline for the sprinkler system must be complete and visable for inspection. |
FAILED |
|
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
|
STORM CONNECTION
Pipe and connection must be visible for inspection. |
PARTIAL |
|
SANITARY CONNECTION
Pipe and connection must be visible for inspection. |
FAILED |
|
WATER CONNECTION
Pipe and connection must be visible for inspection. |
FAILED |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
FAILED |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
FAILED |
|
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
|
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
|
PLUMBING FINAL-OLD
All fixtures must be in place. |
FAILED |
|
PLUMBING FINAL-OLD
All fixtures must be in place. |
FAILED |
|
PLUMBING FINAL-OLD
All fixtures must be in place. |
FAILED |
|
PLUMBING FINAL-OLD
All fixtures must be in place. |
PASSED |
| OCCUPANCY-OLD | FAILED |
| OCCUPANCY-OLD |
PASSED
2005-05-25 |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

View in Google Earth (KML)