BP107447 - 5360 Rutherford -- Drawings Scanned/Attached
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP107447 - 5360 Rutherford -- Drawings Scanned/Attached | |
|---|---|
| Neighbourhood: | Linley Valley |
| Street Address: | 5360 Rutherford -- Drawings Scanned/Attached |
| Type of Application: | Commercial / Multi / Industrial |
| File Number: | BP107447 |
| Date Application Submitted: | May 14, 2004 |
| Application Description: |
First phase of the 25 unit townhouse development - 2 duplexes This permit includes the site servicing and the landscaping 10 Phase multi-family development consisting of 12 duplex and 1 single family dwelling Duplex Block 12, unit 24 - 5747 Garnet Place - 142.88m2, garage 44.46m2 Block 12, unit 22 - 5749 Garnet Place - 142.88m2, garage 50.14m2 Duplex Block 13, unit 25 - 5746 Garnet Place - 142.88m2, garage 50.14m2 Block 13, unit 23 - 5748 Garnet Place - 167.88m2, garage 44.46m2 (bonus room added) March 16, 05 - 25m2 Bonus room added to 5748 Garnet Place creating 2nd floor. 1 hr FRR/fire separation required between suites in this duplex. VS |
| Application Status: | COMPLETED |
| Permit Value: | $482,000.00 |
| Builder: | GEORGIA VIEW HOME BUILDERS LTD |
| Issued Date: | December 10, 2004 |
| File Close Date: | October 12, 2005 |
Associated Properties
| Address | Zone | More |
|---|---|---|
| 5749 GARNET PLACE | R6 | Property Report |
| 5748 GARNET PLACE | R6 | Property Report |
| 5746 GARNET PLACE | R6 | Property Report |
| 5747 GARNET PLACE | R6 | Property Report |
| 5360 RUTHERFORD ROAD | R6 | Property Report |
Process Steps
| Task | Status |
|---|---|
|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
FAILED |
|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
|
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PARTIAL |
|
STORM CONNECTION
Pipe and connection must be visible for inspection. |
CANCELLED |
|
STORM CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
|
SANITARY CONNECTION
Pipe and connection must be visible for inspection. |
CANCELLED |
|
SANITARY CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
|
WATER CONNECTION
Pipe and connection must be visible for inspection. |
CANCELLED |
|
WATER CONNECTION
Pipe and connection must be visible for inspection. |
FAILED |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
|
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
|
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
|
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
|
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
|
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
FAILED |
|
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
|
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
FAILED |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
|
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
FAILED |
|
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
FAILED |
|
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PASSED |
| OCCUPANCY-OLD | FAILED |
| OCCUPANCY-OLD |
PASSED
2005-06-27 |
| OCCUPANCY-OLD |
PASSED
2005-06-29 |
| OCCUPANCY-OLD |
PASSED
2005-07-04 |
| OCCUPANCY-OLD | FAILED |
| OCCUPANCY-OLD |
PASSED
2005-10-12 |
|
FINAL-OLD
Final approval as per requirements on plans. |
FAILED |
|
FINAL-OLD
Final approval as per requirements on plans. |
PARTIAL |
|
FINAL-OLD
Final approval as per requirements on plans. |
PARTIAL |
|
FINAL-OLD
Final approval as per requirements on plans. |
PARTIAL |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

View in Google Earth (KML)