BP106790 - 2000 Boxwood
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP106790 - 2000 Boxwood | |
|---|---|
| Neighbourhood: | Northfield |
| Street Address: | 2000 Boxwood |
| Type of Application: | Commercial / Multi / Industrial |
| File Number: | BP106790 |
| Date Application Submitted: | November 19, 2003 |
| Application Description: |
222.65m Part 9 pre-engineered F-2 warehouse storage building, sprinklered with Fire Alarm. Divided into two F-2 suites with 1 washroom in each, 45 minute fire separation between the suites. One suite being occupied by Jeffrey Construction. Future permit required for any tenent improvements. Occupant load 10 persons for each suite, restricted by washrooms installed. July 7, 04 - Adding 66.9m sprinklered 2nd floor for caretakers dwelling. See BP107700 |
| Application Status: | COMPLETED |
| Permit Value: | $180,000.00 |
| Builder: | J D G CONSTRUCTION |
| Issued Date: | February 20, 2004 |
| File Close Date: | January 22, 2007 |
Associated Properties
| Address | Zone | More |
|---|---|---|
| 2000 BOXWOOD ROAD | I3 | Property Report |
Process Steps
| Task | Status |
|---|---|
|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
|
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
|
FIRELINE
Fireline for the sprinkler system must be complete and visable for inspection. |
PARTIAL |
|
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PASSED |
|
STORM CONNECTION
Pipe and connection must be visible for inspection. |
PARTIAL |
|
SANITARY CONNECTION
Pipe and connection must be visible for inspection. |
PARTIAL |
|
WATER CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
|
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PASSED |
|
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
|
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
|
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PARTIAL |
|
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PASSED |
|
PLUMBING FINAL-OLD
All fixtures must be in place. |
FAILED |
|
PLUMBING FINAL-OLD
All fixtures must be in place. |
PASSED |
|
PLUMBING FINAL-OLD
All fixtures must be in place. |
PASSED |
| OCCUPANCY-OLD | FAILED |
| OCCUPANCY-OLD | FAILED |
| OCCUPANCY-OLD | FAILED |
| OCCUPANCY-OLD |
PASSED
2007-01-22 |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

View in Google Earth (KML)