BP105929 - 6050 Icarus Drive
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP105929 - 6050 Icarus Drive | |
|---|---|
| Neighbourhood: | Dover |
| Street Address: | 6050 Icarus Drive |
| Type of Application: | Single / Two Family Dwelling |
| File Number: | BP105929 |
| Date Application Submitted: | March 19, 2003 |
| Application Description: |
Two story single family dwelling, finished daylight basement, slab / crawlspace, attached garage 2003-Apr-22 - sent to LTO for registration of covenant - Subsidence - cheque # 105824 2003-Apr-28 - covenant registered - EV040565 |
| Application Status: | COMPLETED |
| Permit Value: | $250,000.00 |
| Building Area: |
370.34 M2 3,986.30 ft2 |
| Builder: | WESTMARK CONSTRUCTION LTD |
| Issued Date: | April 23, 2003 |
| File Close Date: | November 19, 2003 |
Associated Properties
| Address | Zone | More |
|---|---|---|
| 6050 ICARUS DRIVE | R1 | Property Report |
Process Steps
| Task | Status |
|---|---|
|
COVENANT PREPARATION
type covenant, applicant to sign, city to notorize. Completed means that the covenant is ready to send to LTO. Completed status will create the task to track LTO registation |
IN-PROGRESS |
|
FOOTING / FORMS
Inspection of forms prior to any concrete being poured |
PASSED |
|
PERIMETER DRAIN
For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering |
PASSED |
|
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible |
PASSED |
|
SANITARY CONNECTION
Pipe and Connection must be visible for inspection |
PASSED |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping |
FAILED |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping |
PASSED |
|
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval |
PARTIAL |
|
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval |
PARTIAL |
|
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval |
PASSED |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
PASSED |
|
OCCUPANCY-OLD
Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish |
FAILED |
|
OCCUPANCY-OLD
Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish |
CANCELLED |
|
OCCUPANCY-OLD
Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish |
FAILED |
|
OCCUPANCY-OLD
Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish |
PASSED
2003-11-19 |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

View in Google Earth (KML)