BP105383 - 1175 Dufferin

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP105383 - 1175 Dufferin
Neighbourhood: Townsite    
Street Address: 1175 Dufferin
Type of Application: Commercial / Multi / Industrial
File Number: BP105383
Date Application Submitted: October 28, 2002
Application Description: xreference Bp105469 for foundation permit
969.49 sq ft one-storey addition at rear and side of existing office, Part 9 building. Demolition of 132.75 sq. ft. New sprinkler system being installed throughout building as required by bylaw. Main floor area = 208m2, two exits required. (changed Dec 17, 2002 ) single exit permitted)Swing exits doors out. Upper floor 118m2; two exits required since the exit stair is exposed to openings that are not protected.

Construction Agreement sent to City Clerks office for signing - Dec. 9, 2002 , signed in file on dec 17, 2002.
Application Status: COMPLETED
Permit Value: $64,000.00
Issued Date: December 09, 2002
File Close Date: March 15, 2004

Process Steps

Task Status
FIRELINE

Fireline for the sprinkler system must be complete and visable for inspection.

CANCELLED
FIRELINE

Fireline for the sprinkler system must be complete and visable for inspection.

CANCELLED
FIRELINE

Fireline for the sprinkler system must be complete and visable for inspection.

PASSED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PASSED
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PASSED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

FAILED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PASSED
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

FAILED
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

PASSED
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

FAILED
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

FAILED
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

FAILED
FINAL-OLD

Final approval as per requirements on plans.

PASSED

2004-03-15

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.