BP105383 - 1175 Dufferin
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP105383 - 1175 Dufferin | |
|---|---|
| Neighbourhood: | Townsite |
| Street Address: | 1175 Dufferin |
| Type of Application: | Commercial / Multi / Industrial |
| File Number: | BP105383 |
| Date Application Submitted: | October 28, 2002 |
| Application Description: |
xreference Bp105469 for foundation permit 969.49 sq ft one-storey addition at rear and side of existing office, Part 9 building. Demolition of 132.75 sq. ft. New sprinkler system being installed throughout building as required by bylaw. Main floor area = 208m2, two exits required. (changed Dec 17, 2002 ) single exit permitted)Swing exits doors out. Upper floor 118m2; two exits required since the exit stair is exposed to openings that are not protected. Construction Agreement sent to City Clerks office for signing - Dec. 9, 2002 , signed in file on dec 17, 2002. |
| Application Status: | COMPLETED |
| Permit Value: | $64,000.00 |
| Issued Date: | December 09, 2002 |
| File Close Date: | March 15, 2004 |
Process Steps
| Task | Status |
|---|---|
|
FIRELINE
Fireline for the sprinkler system must be complete and visable for inspection. |
CANCELLED |
|
FIRELINE
Fireline for the sprinkler system must be complete and visable for inspection. |
CANCELLED |
|
FIRELINE
Fireline for the sprinkler system must be complete and visable for inspection. |
PASSED |
|
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PASSED |
|
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PASSED |
|
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
FAILED |
|
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
|
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
|
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
FAILED |
|
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PASSED |
|
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
FAILED |
|
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
FAILED |
|
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
FAILED |
|
FINAL-OLD
Final approval as per requirements on plans. |
PASSED
2004-03-15 |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

View in Google Earth (KML)