BP103551 - 4316 Boban
Neighbourhood: Diver Lake    
Street Address: 4316 Boban
Type of Application: Commercial / Multi / Industrial
File Number: BP103551
Date Application Submitted: April 20, 2001
Application Description: New Shaw Cablesystems Building (single tenant)
x-reference bp103094 for the foundation permit and on-site servicing. Building Area = 2706.8 m2 (first storey); 2167 m2 Part 3 Building, 2 storeys, non-combustible (required by code), sprinklered (required by code), and gas fire suppression in Head room and Fiber Hub Room. Fire alarm system required by code. Building Classification =3.2.2.51.
1 Hr FRR/FS for floor assemblies and supports.
No rating for roof, Monitored sprinkler system.
Interconnected Floor Area: meets exceptions of 3.2.8.1.(6).
Major Occupancies D, and F2 on main.
Fire separation only between D and F2 -
Occupant Load: 285 persons 1st storey and 269 2nd storey.
Exposure building face and unprotected openings unlimited.
Travel distance 45m maximum. Exits 1hr. enclosure.
Building required to be accessible by code. Accessible toilet room and accessible washrooms.

Application Status: COMPLETED
Permit Value: $6,000,000.00
Builder: SHAW CABLESYSTEMS (BC) LTD
Issued Date: October 22, 2001
File Close Date: October 16, 2003

Associated Properties

Address Zone More
4316 BOBAN DRIVE I2 Property Report

Process Steps

Task Status
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PASSED
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PARTIAL
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PARTIAL
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PARTIAL
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PASSED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PASSED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PASSED
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

FAILED
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

CANCELLED
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

FAILED
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

PASSED
PLUMBING FINAL-OLD

All fixtures must be in place.

CANCELLED
PLUMBING FINAL-OLD

All fixtures must be in place.

PASSED
OCCUPANCY-OLD PARTIAL
OCCUPANCY-OLD FAILED
FINAL-OLD

Final approval as per requirements on plans.

PARTIAL
FINAL-OLD

Final approval as per requirements on plans.

FAILED
FINAL-OLD

Final approval as per requirements on plans.

FAILED
FINAL-OLD

Final approval as per requirements on plans.

PARTIAL
FINAL-OLD

Final approval as per requirements on plans.

PASSED

2003-10-16

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.