BP103204 - 1277 Island Hwy S -- Drawings Scanned/Attached
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP103204 - 1277 Island Hwy S -- Drawings Scanned/Attached | |
|---|---|
| Neighbourhood: | Harewood |
| Street Address: | 1277 Island Hwy S -- Drawings Scanned/Attached |
| Type of Application: | Commercial / Multi / Industrial |
| File Number: | BP103204 |
| Date Application Submitted: | December 04, 2000 |
| Application Description: |
X reference bp103193 for the foundation permit and BP 100973 for the servicing permit(completed) One storey 1233m2, 3.2.2.62, Retail sprinklered combustible accessible Part 3, Shell building. Group E/F2 major occupancies with fire alarm system. Building Shell only. Separate building permits are required for any tenant improvement within the building. Separate of suites 45min FS/FRR. (Typical) No rating for the roof. 1hr FRR on south exterior wall. |
| Application Status: | COMPLETED |
| Permit Value: | $400,000.00 |
| Builder: | WINDLEY CONTRACTING LTD |
| Issued Date: | December 22, 2000 |
| File Close Date: | April 09, 2001 |
Associated Properties
| Address | Zone | More |
|---|---|---|
| 1275 ISLAND HIGHWAY S | CC3 | Property Report |
Process Steps
| Task | Status |
|---|---|
|
FIRELINE
Fireline for the sprinkler system must be complete and visable for inspection. |
PARTIAL |
|
FIRELINE
Fireline for the sprinkler system must be complete and visable for inspection. |
PASSED |
|
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PASSED |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
|
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PASSED |
|
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
|
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
CANCELLED |
|
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
CANCELLED |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
|
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
FAILED |
|
PLUMBING FINAL-OLD
All fixtures must be in place. |
FAILED |
|
PLUMBING FINAL-OLD
All fixtures must be in place. |
FAILED |
|
PLUMBING FINAL-OLD
All fixtures must be in place. |
PASSED |
| OCCUPANCY-OLD | FAILED |
| OCCUPANCY-OLD | FAILED |
| OCCUPANCY-OLD | PARTIAL |
| OCCUPANCY-OLD |
PASSED
2001-04-09 |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

View in Google Earth (KML)