BP102773 - 6190 Strathcona -- Drawings Scanned/Attached

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP102773 - 6190 Strathcona -- Drawings Scanned/Attached
Neighbourhood: Rutherford    
Street Address: 6190 Strathcona -- Drawings Scanned/Attached
Type of Application: Commercial / Multi / Industrial
File Number: BP102773
Date Application Submitted: June 21, 2000
Application Description: X reference, Bp 103505 for the foundation permit and for the on-site servicing permit for Phase 5 and Phase 6.

Phase 5 -
6 duplexes, Part 9 Buildings, sprinklered.
This permit includes on-site servicing for Phase 5 & 6.
Unit #42 -6167 Rosecroft Place,Unit #43 -6165 Rosecroft Place
Unit #44 -6163 Rosecroft Place,Unit #45 -6161 Rosecroft Place
Unit #46 -6159 Rosecroft Place,Unit #47 -6157 Rosecroft Place
Unit #48 -6155 Rosecroft Place,Unit #49 -6153 Rosecroft Place
Unit #50 -6156 Rosecroft Place,Unit #51 -6158 Rosecroft Place
Unit #52 -6160 Rosecroft Place,Unit #53 -6162 Rosecroft Place
Application Status: COMPLETED
Permit Value: $839,760.00
Builder: WINDLEY CONTRACTING LTD
Issued Date: May 25, 2001
File Close Date: September 13, 2001

Process Steps

Task Status
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PASSED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PASSED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PASSED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PARTIAL
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PASSED
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

FAILED
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PARTIAL
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

FAILED
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PASSED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

FAILED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PASSED
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

FAILED
OCCUPANCY-OLD FAILED
OCCUPANCY-OLD PASSED

2001-09-17

FINAL-OLD

Final approval as per requirements on plans.

PARTIAL
Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.