BP101492 - 4870 Hammond Bay (Parent) P 2 -- SL 5-8 VIS 4691

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP101492 - 4870 Hammond Bay (Parent) P 2 -- SL 5-8 VIS 4691
Neighbourhood: North Slope    
Street Address: 4870 Hammond Bay (Parent) P 2 -- SL 5-8 VIS 4691
Type of Application: Commercial / Multi / Industrial
File Number: BP101492
Date Application Submitted: March 31, 1999
Application Description: NEW, sprinklered, combustible fourplex (Units 41 - 44) Part 9 - 1998 BC Building Code applies: 3/4 hour FRR floors, exterior passageway, supports, etc.
See BP101563 for foundation.
Addresses for suites in this building are 4921, 4923, 4925, 4927 Clematis Place.
Application Status: COMPLETED
Permit Value: $215,000.00
Builder: HAZELWOOD CONSTRUCTION SERVICES INC
Issued Date: May 03, 1999
File Close Date: December 16, 1999

Associated Properties

Address Zone More
4923 CLEMATIS PLACE R8 Property Report
4925 CLEMATIS PLACE R8 Property Report
4921 CLEMATIS PLACE R8 Property Report
4927 CLEMATIS PLACE R8 Property Report
4870 HAMMOND BAY ROAD R8 Property Report

Process Steps

Task Status
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PASSED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PASSED
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

CANCELLED
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PASSED
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

CANCELLED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PASSED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

FAILED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

FAILED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

FAILED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PASSED
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

PARTIAL
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

PASSED
PLUMBING FINAL-OLD

All fixtures must be in place.

PASSED
OCCUPANCY-OLD PASSED

1999-12-16

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.