File Number: BP100023
Date Application Submitted: December 02, 1997
Application Description: New commercial shell building on top of Harbourfront Plaza Parkade. (Credit Union Building)
Building classification 3.2.2.22. A2 , sprinklered with fire alarm
Non- combustible construction. Total area: 2099m2
Major occupancies: Group D upper Floor
Group A2, Group E lower floor
Group F3 , Parkade, previous perrmit
Occupancy separation: D/A2 - 1 hour
E/A2 - 2 hours
Spatial: 45min.
Exits: 2 required/provided each suite
Washroom: 34 roughin plumbing fixtures charged on this permit
Future permits required for tenant improvements.
Application Status: COMPLETED
Permit Value: $1,300,000.00
Issued Date: February 02, 1998
File Close Date: November 05, 1998

Associated Properties

Address Zone More
59 WHARF STREET DT1 Property Report

Process Steps

Task Status
STORM CONNECTION

Pipe and connection must be visible for inspection.

CANCELLED
SANITARY CONNECTION

Pipe and connection must be visible for inspection.

PARTIAL
WATER CONNECTION

Pipe and connection must be visible for inspection.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

FAILED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PASSED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PASSED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

PARTIAL
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

PARTIAL
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

PASSED
PLUMBING FINAL-OLD

All fixtures must be in place.

PASSED
OCCUPANCY-OLD PASSED

1998-11-05

FINAL-OLD

Final approval as per requirements on plans.

PARTIAL
Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.