BP120498 - 380 Fifth Street

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP120498 - 380 Fifth Street
Neighbourhood: University District    
Street Address: 380 Fifth Street
Type of Application: Commercial / Multi / Industrial
File Number: BP120498
Date Application Submitted: December 18, 2014
Application Description: Multi- family/Row housing, 8 Residential units. 3 Storey, Part #9 Building, combustible construction, 1 hr FS/FRR Party wall with STM rating of 50 required to underside of roof sheathing between each unit. Property to be subdivided into 8 separate lots prior to framing inspection.

1st floor = 36.23 m2
2nd floor = 56.67 m2
3 rd floor =58.44
Total Per unit = 151.34 m2 X (8 units) = Total floor area = 1210.72 m2
Each unit has an additional attached garage area of 22.76 m2

Oct 2, 2015 - Revision: Add Geotechnical Engineer.
Application Status: COMPLETED
Permit Value: $1,751,711.28
Builder: SAYWELL DEVELOPMENTS LTD
Issued Date: June 09, 2015
File Close Date: November 25, 2016
Expiry Date: June 09, 2017

Associated Properties

Address Zone More
481 STIRLING AVENUE R1 , R7 Property Report
483 STIRLING AVENUE R1 , R7 Property Report
485 STIRLING AVENUE R1 , R7 Property Report
487 STIRLING AVENUE R1 , R7 Property Report
489 STIRLING AVENUE R1 , R7 Property Report
491 STIRLING AVENUE R1 , R7 Property Report
493 STIRLING AVENUE R1 , R7 Property Report
495 STIRLING AVENUE R1 , R7 Property Report

Process Steps

Task Status
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PARTIAL
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PARTIAL
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PARTIAL
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PARTIAL
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PASSED
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete.

PASSED
SANITARY CONNECTION

Pipe and connection must be visible for inspection.

PARTIAL
SANITARY CONNECTION

Pipe and connection must be visible for inspection.

PASSED
WATER CONNECTION

Pipe and connection must be visible for inspection.

PARTIAL
WATER CONNECTION

Pipe and connection must be visible for inspection.

PASSED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PASSED
LATERAL BRACING & SHEATHING

All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors.

PARTIAL
LATERAL BRACING & SHEATHING

All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors.

PASSED
LATERAL BRACING & SHEATHING

All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors.

SCHEDULED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PARTIAL
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PARTIAL
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PASSED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PASSED
INTERIOR BRACED WALL PANELS

The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound.

PARTIAL
INTERIOR BRACED WALL PANELS

The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound.

PARTIAL
INTERIOR BRACED WALL PANELS

The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound.

PARTIAL
INTERIOR BRACED WALL PANELS

The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound.

PASSED
MONITORING FIELD REVIEW

A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional.

PARTIAL
OCCUPANCY-OLD FAILED
OCCUPANCY-OLD PARTIAL
FINAL-OLD

Final approval as per requirements on plans.

PARTIAL
FINAL-OLD

Final approval as per requirements on plans.

PASSED

2016-11-25

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

Help us improve our website

Don't include private or financial information in this form.

Collection and use of your personal information
Information collected on this form is done so under the general authority of the Community Charter and Freedom of Information and Protection of Privacy Act (FOIPPA), and is protected in accordance with FOIPPA.  Personal information will only be used by authorized staff to fulfill the purpose for which it was originally collected, or for a use consistent with that purpose. Questions about the collection of your personal information may be referred to the Legislative Services Department at (250) 755-4405, or via email at foi@nanaimo.ca.
Privacy Policy