BP117211 - 31 White Eagle Terrace

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP117211 - 31 White Eagle Terrace
Neighbourhood: Departure Bay    
Street Address: 31 White Eagle Terrace
Type of Application: Single / Two Family Dwelling
File Number: BP117211
Date Application Submitted: April 03, 2012
Application Description: for construction of a two storey single family dwelling with slab on grade.

Revision. Changes to roof layout. A Few windows deleted sizes changed. 2013-11-03
Application Status: COMPLETED
Permit Value: $700,000.00
Building Area: 412.29 M2
4,437.85 ft2
Builder: COLLINS CUSTOM CONTRACTING
Issued Date: June 19, 2012
File Close Date: September 12, 2013

Associated Properties

Address Zone More
31 WHITE EAGLE TERRACE R1 Property Report

Process Steps

Task Status
FOOTING / FORMS

Inspection of forms prior to any concrete being poured

PASSED
FOOTING / FORMS

Inspection of forms prior to any concrete being poured

PARTIAL
FOOTING / FORMS

Inspection of forms prior to any concrete being poured

PASSED
PERIMETER DRAIN

For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering

PARTIAL
PERIMETER DRAIN

For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering

PARTIAL
PERIMETER DRAIN

For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering

PARTIAL
UNDERSLAB PLUMBING

Complete underslab plumbing must be visible

PASSED
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete

PASSED
STORM CONNECTION

Pipe and Connection must be visible for inspection

CANCELLED
SANITARY CONNECTION

Pipe and Connection must be visible for inspection

CANCELLED
SANITARY CONNECTION

Pipe and Connection must be visible for inspection

PASSED
WATER CONNECTION

Pipe and Connection must be visable for inspection

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping

PARTIAL
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PARTIAL
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PASSED
FRAMING

Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval

PARTIAL
FRAMING

Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval

PARTIAL
FRAMING

Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval

PASSED
INSULATION

Insulation and vapour barrier to be complete prior to inspection

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection

PASSED
MONITORING FIELD REVIEW PASSED
MONITORING FIELD REVIEW PASSED
MONITORING FIELD REVIEW PARTIAL
OCCUPANCY-OLD

Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish

FAILED
OCCUPANCY-OLD

Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish

PASSED

2013-09-12

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

Help us improve our website

Don't include private or financial information in this form.

Collection and use of your personal information
Information collected on this form is done so under the general authority of the Community Charter and Freedom of Information and Protection of Privacy Act (FOIPPA), and is protected in accordance with FOIPPA.  Personal information will only be used by authorized staff to fulfill the purpose for which it was originally collected, or for a use consistent with that purpose. Questions about the collection of your personal information may be referred to the Legislative Services Department at (250) 755-4405, or via email at foi@nanaimo.ca.
Privacy Policy