Albert Street Phase 3 - Mobility Upgrades

The Albert Street Phase 3 Mobility Upgrades project consists of two major components:
- Installation of two new raised crosswalks, including pedestrian flashers at both Selby Street and at Dunsmuir Street.
- Continuation of the VIU Bikeway on Albert Street from Milton Street to Cavan Street.
Did you know? VIU is currently the City's largest cycling destination.
Milestone Equipment Contracting Inc, on behalf of the City of Nanaimo, will begin construction on February 2nd, 2026. Construction signage is located along the corridor and construction notices have been delivered to adjacent property owners.
This is the third phase of the Albert / Fourth Street project. Phase 1, which ran from Harewood Road to Pine Street, was completed in the Summer of 2022. Phase 2, which ran from Pine Street to Milton Street was completed in the Spring of 2024. Phase 3, which runs from Milton Street to Cavan Street will be completed by Spring 2026.
Project Area:
Check out the additional information under the tabs below, a Q&A forum, background information, and more!
Questions?
Email Albert.Street@nanaimo.ca | Phone 250-756-5321
- Progress
CONSTRUCTION UPDATE:
ROAD CLOSURE: Albert Street will be closed between Milton Street and Prideaux Street from March 18 to March 19, 2026, to facilitate a railway crossing upgrade (Detour Map). The work will be undertaken by Milestone Equipment Contracting, Amrize, and the Southern Railway of Vancouver Island and has been coordinated with the ongoing Albert Street construction to minimize overall disruption. The closure will be in effect 24 hours/day for the duration of the work, as the rail crossing will be impassable during construction.
Construction notices were hand delivered to adjacent property owners.
The end is near! Construction is scheduled to be complete by the end of March 2026.
------
Milestone Equipment Contracting Inc. will begin work on February 2, 2026. Please adjust your commute to avoid delays.
Construction signage is up and construction notices were hand delivered to adjacent property owners.
PROJECT SCHEDULE:
Phase: Timeframe: Public Consultation Summer 2021: Complete Phase 1 Construction Fall 2021 - Summer 2022: Complete Phase 2 Construction Spring 2023 - Spring 2024: Complete Phase 3 Construction February 2, 2026 - Construction Begins Feb 2 - Mar 13: Drainage Upgrades & Concrete Islands March 16 - 20: Railway Crossing Upgrade & Bus Stops March 23 - 27: Raised Crosswalks & Roadmarkings March 31, 2026 - Construction Complete - Documents
- Details
Additional Construction FAQs that are not project specific, can be found here: City Construction Project FAQS
Frequently Asked Questions
Q: Why is the City constructing a bikeway on Albert Street?
The bikeway on Albert & Fourth Streets will provide the shortest and most direct route between the Downtown Mobility Hub and Vancouver Island University Mobility Hub.
Q: What public support has been expressed in favour of cycling facilities?
Support for cycling facilities has been generated through various public consultation initiatives such as the ‘Nanaimo Transportation Master Plan’, the ‘Downtown Nanaimo Mobility Hub Project’ and ‘City Plan: Nanaimo ReImagined’.
Q: Can I see the design?
Yes, you can find the Albert St Phase 3 drawing here.
Q: Will there be a loss of parking?
Yes, parking will be removed from the south/east side of Albert Street; however parking will remain on the north/west side.
Q: Will Albert Street maintain two-way traffic?
Yes. Albert street will continue to operate with two-way traffic. One lane of parking has been removed, but the final design includes a travel lane and bike lane in each direction, with parking remaining on one side of the street.
Q: What are the concrete islands for?
The concrete islands intentionally separate the travel lane, parking lane, and bike lane. At intersections, the islands help prevent vehicles from mistakenly turning in the parking lane instead of the intended travel lane.
Q: What safety features will the design include?
- City projects include safety improvements from the Provincial Government’s BC Community Road Safety Toolkit, created in the hopes of working towards Vision Zero in communities throughout the province.
- Pedestrian & Cycling Safety Improvements included on Albert Street:
- Tactile Warning Surface Indicators (TWSIs)
- Refuge Islands & Curb Extensions (Module1 - Page10)
- Protected Bicycle Lanes (Module1-Page12)
- Complete Street Design & Road Diets (Module1 - Page13)
- Floating Bus Stop (Module1 - Page20-21)
- Raised Crossings (Module1 - Page26)
- Roadway Safety Improvements included on Metral Drive:
- Narrowed Vehicle Lanes (Module2 - Page7)
- Smaller Corner Radii (Module2 - Page24)
Q: Will my commute be affected?
If you normally use Albert Street during your commute, we suggest that you use an alternate route to avoid delays. Work areas within the project area will be subject to one-way alternating traffic conditions during construction. If you live directly adjacent to the project, and cannot avoid the area roads, please leave yourself extra time.
Q: Why did construction start and then stop?
Paving cannot occur during winter months due to lower than ideal temperatures for asphalt placement. Albert Street remains in the queue with other projects around town waiting for temperatures to warm up and sub-contractor availability.
Q: When will construction be complete?
Construction is expected to be complete by the end of March. The remaining work includes installation of the raised crosswalks and final markings, which are scheduled to be complete by March 31st.
- Background
Give feedback on accessibility. Submit your feedback through our online accessibility feedback form. Help us understand barriers people face when accessing City services.
You can attach files to help explain the barrier you faced in the form, like: a video, voice recording or photos. If American Sign Language (ASL) is the best way for you to communicate, upload a video of yourself using ASL into the form.
Please include: what you were trying to access, where the barrier happened, what the barrier was and any recommendations you might have.
Help us improve our website
Important Information About Privacy
Information collected on this form is done so under the general authority of the Community Charter and Freedom of Information and Privacy Protection Act (FOIPPA), and is protected in accordance with FOIPPA. Personal information will only be used by authorized staff to fulfill the purpose for which it was originally collected, or for a use consistent with that purpose.
For further information regarding the collection, use, or disclosure of personal information, please contact the Legislative Services Office at 250-755-4405 or at foi@nanaimo.ca
-
Parks, Rec & Culture
- Recreation Facilities & Schedules
- Parks & Trails
- Trails
- Activity Guide
- Events
- Register for a Program
- Drop-In Schedules
- Public Art
- Culture
- Poetry
-
City Services
- Garbage & Recycling
- Home & Property
- Water & Sewage
- Online Services
- Cemetery Services
- City Services Directory
-
Property & Development
- Urban Forestry
-
Building Permits
- Online Building Permit Application
- Building Permit Revision
-
Application for a Residential Building Permit
- Access (driveway) Permit
- Accessory Building Permit
- Alteration Permit
- Building Envelope Repair
- Carriage House
- Demolition Permit
- Fence or Retaining Wall Permit
- Geotechnical Reports
- Locate Permit
- New Construction Permit
- Plumbing or Services Permit
- Secondary Suite Permit
- Special Inspection Permit
- Swimming Pool Permit
- Woodstove Installation Info
- Green Home Initiatives
- Small-Scale Multi-Unit Housing (SSMUH) Permit
-
Apply for a Commercial Building Permit
- Access (driveway) Permit
- Commercial Alteration Permit
- Building Envelope Repair Permit
- Demolition Permit
- Fence or Retaining Wall Permit
- Geotechnical Reports
- Leasehold Improvement
- Locate Permit
- New Commercial Construction Permit
- Occupant Load Permit
- Signs Permit
- Special Inspection Permit
- Sprinkler Requirements
- Fees and Bonding
- Commercial Plumbing Permit
- Certified Professional Program
- Bylaws for Building
- Forms and Guidelines
- Book a Building Inspection
- Report Illegal Construction
- Request Building Plans
- Building Permit Statistics
- Permit Fee Calculator
- Building News and Alerts
- Fast Track Building Permits
- Development Information
- What's Building in my Neighbourhood
- Development Activity Map
- Community Planning
- NanaimoMap
- Rebates
- Engineering Survey
- Land Use Bylaws
- Soil Removal and Depositing
- Heritage Buildings
- Sustainability
- Transportation & Mobility
-
Your Government
- Get Involved
- Government Services Guide
- News & Events
-
City Council
- Advocacy
- Contact Mayor & Council
- Council Meetings
-
Boards & Committees
- Advisory Committee on Accessibility and Inclusiveness
- Board of Variance
- Design Advisory Panel
- Finance and Audit Committee
- Governance and Priorities Committee
- Mayor's Leaders' Table
- Parcel Tax Roll Review Panel
- Special District 68 Sports Field and Recreation Committee
- Public Safety Committee
- Understanding Council Committee Structures
- Council Policies
- Mayor's Office
- Council Initiatives
- Proclamations
- Bastion Lighting Requests
- Alternative Approval Process
- Budget & Finance
- Records, Information & Privacy
- Elections
- Contacts
- Careers
- Maps & Data
- Projects
- Tourism Nanaimo
- Grants
- Awards
- Accessibility & Inclusion
-
Doing Business
- Economic Development
- Doing Business with the City
- Business Licences
- Filming in Nanaimo
- City Owned Property
- Encroachments onto City Property
- Liquor Licences
- Cannabis Retail
- Business Improvement Areas
- Procurement Services
- About Nanaimo
- Green Initiatives
-
Public Safety
- Social Development
- Public Safety Contacts
- Nanaimo Fire Rescue
- Emergency Management
- Police & Crime Prevention
- City Bylaws
- Community Safety and Wellbeing
- Emergency Services

