BP122087 - 10 Church Street (Main)
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP122087 - 10 Church Street (Main) | |
---|---|
Neighbourhood: | Downtown/Old City |
Street Address: | 10 Church Street (Main) |
Type of Application: | Commercial / Multi / Industrial |
File Number: | BP122087 |
Date Application Submitted: | June 08, 2016 |
Application Description: |
2 storey addition to an existing commercial building. Building classified as 3.2.2.59 Group D up to 3 storeys, sprinklered,fire alarm system. All floors are accessible via an elevator, each floor has 2 means of egress. Work to include plumbing and accessible washrooms. 45 min FRR for exits. 2HR FRR exterior perimeter walls. Alternative solution report for Elevator in exit stair enclosure, Glazing in Fire Separation, and Protection of Openings at Property Line Nov 16 REVISION - Alter the elevator layout and addition of an accessible shower to the bicycle room. REVISION: Feb. 6/18 - Add office and closet to CRU (Unit #12) Group D Occupancy. Add meeting room to 3rd floor with sink. delete sink from 2nd floor. Relocate exit doors, increase windows. |
Application Status: | COMPLETED |
Permit Value: | $1,613,974.00 |
Builder: | RW (BOB) WALL LTD |
Issued Date: | September 01, 2016 |
File Close Date: | February 28, 2018 |
Expiry Date: | September 01, 2018 |
Associated Properties
Address | Zone | More |
---|---|---|
10 CHURCH STREET | DT1 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
FAILED |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
CANCELLED |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PARTIAL |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PASSED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
FAILED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
CANCELLED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
FAILED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
CANCELLED |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PARTIAL |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PASSED |
PLUMBING FINAL-OLD
All fixtures must be in place. |
PARTIAL |
PLUMBING FINAL-OLD
All fixtures must be in place. |
PASSED |
APPROVAL-FIRE-OLD
Approval required prior to Occupancy |
COMPLETED |
FINAL-OLD
Final approval as per requirements on plans. |
FAILED |
FINAL-OLD
Final approval as per requirements on plans. |
PASSED
2018-02-28 |
Map |
---|
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.