BP121528 - Unit #102 - 679 Terminal Avenue
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP121528 - Unit #102 - 679 Terminal Avenue | |
---|---|
Neighbourhood: | Newcastle/Brechin |
Street Address: | Unit #102 - 679 Terminal Avenue |
Type of Application: | Leasehold Improvements |
File Number: | BP121528 |
Date Application Submitted: | December 18, 2015 |
Application Description: |
Tenant Improvement: Unit #102, 194.26m2, Group A2 occupancy, "KIDS CO"(daycare). New building classification: Group A div 2, 3.2.2.27, combustible construction,2 storey, Mixed-use building, sprinklered with fire alarm. Original building classification: Part 9, Two storey, Mixed-use building, sprinklered with fire alarm, first storey 450 m2 (existing 290.97m2), second storey 311m 2. First storey divided into 3 "Shell"" Group D" suites, with a 1 hr fire resistance rating/fire separation (FRR/FS) provided between the 1st storey units and one hour FRR/FS/50 STM provided between the first and second storey. Shell "Group D" 1st storey: #101=127.88 m2 (single exit); #102= 194.26 m2 (2 exits); #103 = 117.17 m2 (single exit); 2nd storey divided into 3 residential dwelling units with a 1 hr FRR/FS/50 STM between units and between 1st and 2 nd storey. Exiting from Residential units via rear exit stairs, openings in 1st storey protected with wired glass in steel frames. |
Application Status: | COMPLETED |
Permit Value: | $100,000.00 |
Issued Date: | March 03, 2016 |
File Close Date: | May 09, 2016 |
Expiry Date: | March 05, 2018 |
Associated Properties
Address | Zone | More |
---|---|---|
102 679 TERMINAL AVENUE N | COR2 | Property Report |
679 TERMINAL AVENUE N | COR2 | Property Report |
Process Steps
Task | Status |
---|---|
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible. |
PASSED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visible for inspection. |
PASSED |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval. |
CANCELLED |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval. |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
PLUMBING FINAL-OLD
All fixtures must be in place. |
PARTIAL |
PLUMBING FINAL-OLD
All fixtures must be in place. |
PASSED |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PARTIAL |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PASSED |
FINAL-OLD
Final Approval as per requirements on plans. |
FAILED |
FINAL-OLD
Final Approval as per requirements on plans. |
PARTIAL |
FINAL-OLD
Final Approval as per requirements on plans. |
PASSED
2016-05-09 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.