Type of Application: Leasehold Improvements
File Number: BP119556
Date Application Submitted: March 20, 2014
Application Description: UNIT- 6 - combining units 6-10
Kidney Care Clinic (VIHA) Group D, accessible - 332.87 m2, (existing 6-9), 2 exits required, exits at front with a min of 9 meters between the exits. One exit is through existing 45 min FRR/FS exit corridor and demising wall. Adding 1 washroom and 1 universal washroom, 8 sinks in clinic rooms, accessible section at reception desk to be provided.
Kidney Care Clinic (classroom) (VIHA) Group D, 82.8 m2, (existing 10) south building, 1 exit required, exits at front , meets distance for single exit. 45 min FRR roof rating. Occupant load = 30 persons. 2 universal washooms.

Existing, unsprinklered combustible buildings. See Bp101074 for equivalency report. North building = 713 m2 ~Area recalcuated under BP116252. Two storey, Group E and D, joined by an existing unenclosed walkway between buildings. Two storey, South building Group E/D and A2, 3.2.2.25 (current code reference) 1245m2~. (by existing equivalency under BP101074 (1998 code)
Application Status: COMPLETED
Permit Value: $361,500.00
Building Area: 415.67 M2
4,474.23 ft2
Builder: TECTONICA MANAGEMENT INC
Issued Date: April 24, 2014
File Close Date: August 20, 2015
Expiry Date: April 25, 2016

Associated Properties

Address Zone More
1588 BOUNDARY CRESCENT CC5 Property Report

Process Steps

Task Status
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
FRAMING

Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval.

PARTIAL
FRAMING

Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval.

PARTIAL
FRAMING

Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval.

PASSED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PASSED
PLUMBING FINAL-OLD

All fixtures must be in place.

PASSED
FINAL-OLD

Final Approval as per requirements on plans.

FAILED
FINAL-OLD

Final Approval as per requirements on plans.

FAILED
FINAL-OLD

Final Approval as per requirements on plans.

PASSED

2015-08-20

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

Help us improve our website

Don't include private or financial information in this form.

Collection and use of your personal information
Information collected on this form is done so under the general authority of the Community Charter and Freedom of Information and Protection of Privacy Act (FOIPPA), and is protected in accordance with FOIPPA.  Personal information will only be used by authorized staff to fulfill the purpose for which it was originally collected, or for a use consistent with that purpose. Questions about the collection of your personal information may be referred to the Legislative Services Department at (250) 755-4405, or via email at foi@nanaimo.ca.
Privacy Policy