The project design phase began in late 2018 and is expected to be complete by the end of 2019. Construction is planned to begin in 2020 and be complete by the end of 2022. Additional progress updates will be made available below as the project progresses.
Project Updates
• July 11, 2019: Public Information session held at 666 Fitzwilliam Street.
• July 2019: The project is currently in the design phase.
• January 22, 2020: Design has been completed and the Project has been issued for tender.
• May 12, 2020: The tender has period has closed.
• June 26, 2020: Construction contract has been awarded to Kinetic Construction Ltd.
• June 17, 2020: Project budget updated and increased from $17M to $20M
• July 27, 2020: Began Construction
• October 5th, 2020: Construction in Progress (see below).

• January 4, 2021: Construction in Progress (see below).

• March 22, 2021: Construction in Progress (see below).

• May 25, 2021: Construction in Progress (see below).

• July 19, 2021: Construction in Progress (see below).

• September 20, 2021: Construction in Progress (see below).

• November 10, 2021: Construction in Progress (see below).

• January 17, 2022: Construction in Progress (see below).

• March 23rd, 2022: Construction in Progress (see below).

• May 16th, 2022: Construction in Progress (see below).

• July 21st, 2022: Construction in Progress (see below).

• October 6th, 2022: Construction in Progress (see below).
