Commercial Street Improvements - Wharf to Church Streets

Back to map

Project Description

The Commercial Street Improvements Project consists of:

  • Watermain Replacement
  • Pedestrian and Street Lighting
  • Concrete Sidewalk
  • Concrete Road
  • Landscaping
  • Public Art
  • Street Furnishing

General Considerations

  • Typical hours of work for this project will be Monday to Friday, 7:00 AM to 5:00 PM, with work after hours and weekends as required.
  • Downtown businesses remain open as usual.
  • Free 2 hour on-street parking is available downtown during the project.
  • Commercial Street from Wharf Street to Church Street will not be accessible by vehicles.
  • Bastion Street at Commercial is subject to intermittent Single Lane Alternating traffic.

Construction Value: $5,800,000.00

Estimate Construction Start Date: September 3, 2024

Estimate Construction Completion Date: July, 2025