Departure Bay Area Utility Upgrade

Back to map

Project Description

The Departure Bay Area Utility Upgrade Project consists of the installation of approximately 1,250m water main, 290m of sanitary sewer main, a sanitary sewer siphon with creek crossing, 580m of storm main, ditch infill, and asphalt paving.

The work area is divided into the following areas:

Glenayr Drive (from Loat to Bay)

  • Water Main Upgrade
  • Sewer Main Upgrade
  • Ditch Infill and Storm Main Installation
  • Full Width Paving

Bay Street (from James to Keighley)

  • Water Main Upgrade

Bay Street (from Glenayr to Fairbanks)

  • Storm Sewer Upgrade

Norfolk Hill

  • Water Main Upgrade

Haliday Crescent (from Norfolk to Bay)

  • Water Main Upgrade

Wingrove Street (from Glenayr to Elk)

  • Water Main Upgrade

James Street to Deerborne

  • Sanitary Sewer Siphon

A link below under the Documents section will be available after construction begins to provide a description of the schedule by zone. Schedule updates will be posted periodically throughout the project.

General Considerations

  • Typical hours of work for this project will be Monday to Friday, 7:00 AM to 5:00 PM, with work after hours and weekends as required.
  • Construction noise and vibration should be expected during working hours.
  • Residents and businesses will be notified 24 hours in advance of any scheduled water shutdowns.
  • Anticipate traffic pattern changes - Construction signs will be posted and flag persons will be on duty to assist with the traffic flow.
  • If you live in the area and have young children, please advise them of the dangers and limited visibility of heavy equipment and trucks.
  • Landscape restoration will be done at the end of the project.

Cost Estimate:

Estimate Construction Start Date: March 2018

Estimate Construction Completion Date: October 2018