Terminal Avenue Utility Upgrades

Back to map

Project Description

Terminal Avenue Utility Upgrade Project consists of the installation of approximately 300m of watermain, 1400m of sanitary sewer main, 675m of PVC DR35 storm sewer main, 7500m^2 of asphalt pavement restoration and all other work incidental. The work area is divided into 5 zones as follows:

  • Zone 1 – Terminal Avenue from St. George to Stewart Avenue
  • Zone 2 – Cypress Street
  • Zone 3 – Mount Benson Street
  • Zone 4 – Dawes Street
  • Zone 5 – Bradley, Holly, and Wall Street

A link below under the Documents section will be available after construction begins to provide a description of the schedule by zone. Schedule updates will be posted periodically throughout the project.

General Considerations

  • Typical hours of work for this project will be Monday to Friday, 7:00 AM to 5:00 PM, with work after hours and weekends as required.
  • Construction noise and vibration should be expected during working hours.
  • Residents and businesses will be notified 24 hours in advance of any scheduled water shutdowns.
  • Traffic on Terminal Avenue will be a minimum of two way during the day (5am – 9pm) and single lane alternating traffic at night (9pm – 5am). Detours may also be in effect at night.
  • Traffic on Cypress, Dawes, Mt.Benson, Bradley, Holly, Wall will be open to local traffic and closed to through traffic during construction.
  • Landscape restoration will be done at the end of the project.

Cost Estimate:

Estimate Construction Start Date: April 2017

Estimate Construction Completion Date: Jan 2018

For More Information: http://www.nanaimo.ca/EN/main/departments/Engineering-Public-Works/EngineeringProjects/terminal-ave-upgrade.html

Contact
Construction Department

Documents

Images

terminalavenueutilityupgradezonemap.png

Map

Download Data:

Help us improve our website

Don't include private or financial information in this form.