Rosstown Sanitary Sewer Upgrade

Back to map

Project Description

Starting Wednesday, October 25, 2017, the City of Nanaimo will be upgrading the sanity sewer in your area. Construction is anticipated to be complete within 3 weeks.

During this construction period traffic disruptions can be expected. Flagperson will assist and direct access to your property as needed. Construction signs will be posted and flagpersons will be on duty to assist with the traffic flow. Please exercise caution, obey all signage placed for your safety, and follow the directions of the flagpersons on duty.

If you have any questions during construction the following people will be at the job site to assist you:

General Considerations

  • Construction noise and vibration should be expected during working hours. Typical hours of work for this project will be Monday to Friday, 8 a.m. to 5 p.m. with after hours and weekends as required.

  • Residents and businesses will be notified 24 hours in advance of any scheduled water shutdowns.

  • No read closures are planned, but traffic will be reduced to single lane alternating. Please use an alternate route when possible.

  • Landscape restoration will be done at the end of the project.

Cost Estimate:

Estimate Construction Start Date: October 25, 2017

Estimate Construction Completion Date: November 22, 2017