BP122038 - 5282A Somerset Drive

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP122038 - 5282A Somerset Drive
Neighbourhood: Pleasant Valley    
Street Address: 5282A Somerset Drive
Type of Application: Accessory Building
File Number: BP122038
Date Application Submitted: May 27, 2016
Application Description: Carriage House

REVISION- Slab changed to crawlspace. ICF used for foundation.

REVISION-Change living room and kitchen window sizes. Changed layout in bedrooms upstais and kitchen. Moved garage to house door. Added door at rear of building.

REVISION-Brace wall changes.
Application Status: HOLDBACK
Permit Value: $90,000.00
Building Area: 83.15 M2
895.02 ft2
Builder: KEVIN STEPHEN BAUMANN
Builder: JENNIFER ALICE MARIE BAUMANN
Issued Date: August 03, 2016
Completed Date: December 18, 2017
Expiry Date: August 03, 2018

Associated Properties

Address Zone More
5282 SOMERSET DRIVE R1 Property Report

Process Steps

Task Status
EXCAVATION

Excavation of soil, prior to placing forms.

PASSED
FOOTING/FORMS

Inspection of Forms prior to any concrete being poured for footing inspection. Forms must be complete and approved plans (complete with City Stamp) must be onsite.

PARTIAL
FOOTING/FORMS

Inspection of Forms prior to any concrete being poured for footing inspection. Forms must be complete and approved plans (complete with City Stamp) must be onsite.

PASSED
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

SCHEDULED
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PARTIAL
WATER CONNECTION

Pipe and connection must be visible for inspection.

FAILED
WATER CONNECTION

Pipe and connection must be visible for inspection.

PARTIAL
SANITARY CONNECTION

Pipe and Connection must be visible for inspection.

FAILED
SANITARY CONNECTION

Pipe and Connection must be visible for inspection.

PASSED
STORM CONNECTION

Pipe and Connection must be visible for inspection

PASSED
STORM CONNECTION

Pipe and Connection must be visible for inspection

FAILED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

SCHEDULED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
LATERAL BRACING & SHEATHING

All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors.

FAILED
LATERAL BRACING & SHEATHING

All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors.

PASSED
LATERAL BRACING & SHEATHING

All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors.

FAILED
LATERAL BRACING & SHEATHING

All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors.

FAILED
LATERAL BRACING & SHEATHING

All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors.

CANCELLED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

CANCELLED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PARTIAL
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

CANCELLED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PARTIAL
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PASSED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

SCHEDULED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PASSED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

CANCELLED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

FAILED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

FAILED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

CANCELLED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

FAILED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PASSED
INTERIOR BRACED WALL PANELS PASSED
INTERIOR BRACED WALL PANELS FAILED
INTERIOR BRACED WALL PANELS FAILED
INTERIOR BRACED WALL PANELS CANCELLED
OCCUPANCY

Occupancy inspection to be used for new accessory suite (Carriage House). Covenant must be registered on title, HPO in place, private outdoor space must be provided for occupants, one onsite parking spot

PASSED
FINAL

Final approval as per requirements on plans.

FAILED
Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

Help us improve our website

Don't include private or financial information in this form.